The suspended Ɓagwai Irrigation Project debacle
By Muhammad Ahmad Iliasu.
In May 2021, the Federal Executive Council (FEC) approved a sum of ₦3.76 billion as augmentation for the existing and ongoing expansion and completion of the Ɓagwai Irrigation Project on Watari Dam in the Ɓagwai local government area of Kano state.
The project was awarded to Messrs Ɗantata and Sawoe Construction Company Limited, mobilised in 2006 for an initial period of two years. The scope of work was a special irrigation scheme involving 872 hectares. The contract had been ongoing but ran into many problems and was suspended at some points due to lack of funding. Thus, the audit and seeking ₦3.76 billion augmentation bring the new contract sum to ₦9.2 billion from ₦5.4 billion, inclusive of 7.5 per cent VAT, with an additional completion period of 24 months plus another 12 months liability period.
Additionally, the then Minister of Water Resources, Hon. Sulaiman Adamu, told State House correspondents after the virtual FEC meeting presided over by Vice President Yemi Osinbajo at the Presidential Villa, Abuja, “We hope that these projects will be implemented in earnest and hopefully, we will be able to get them completed by 2023 for the overall benefit of the people.’’
Unfortunately, as of today, November 10, 2024, the project has not progressed further and has been declared suspended by those who have close contact with the contractors, despite the open revelations made by the former Minister of Water Resources in 2021.
Revealed in a WhatsApp conversation between a stakeholder in the Ɗantata and Sawoe company and one of the farmers desperately praying for when the project will be revisited and completed, the reason for the suspension of the irrigation project in Ɓagwai is the unprecedented instability in exchange rates.
In a fresh setback encountered by the Ɓagwai irrigation project once again, the augmentation, the stakeholder said, was approved when ₦398 was approximately exchanged for $1. But since then, the rate has astronomically risen to ₦448 for $1 in 2022, ₦638 for $1 in 2023, and ₦1,724 for $1 in 2024, respectively. The worsening of the local currency is the single most determining factor between the project and any identifiable progress. If any activity were to resume, the federal government had to revise the audit and account for the unprecedented change in the project cost.
Meanwhile, as the project hits another roadblock, the hardworking farmers, who might not understand the causes frustrating their industry, have grown severely disturbed by their inability to use their farmlands, which are the construction site of a long-suspended project. Many are subsistence farmers who rely on the place to feed their families. Another massive number of farmers rely on the place to make a living.
The anticipation of the continuation of the project hindered most of the farmers from cultivating the farmlands because they didn’t know when the project would resume, and they feared having their season interrupted. The condition of the farmlands, as caused by the start of the suspended canalisation, has rendered most of it uncultivable.
Most farmers have grown confused and fear that the Watari Dam Renovation project in Ɓagwai by the Kano State Government in collaboration with the Islamic Development Bank, has taken the spotlight away from the Federal Government’s expansion of the irrigation sectors. The project has also misled stakeholders into thinking it is ongoing,when indeed it is far from being so. And they’re right to be concerned.
The euphoria surrounding the Watari Dam Renovation was overflogged during the 2023 election campaigns and gubernatorial debates. Unintentionally, this distracted the public from the real ghost in the machine: very few people knew that the projects were separate and dissimilar.
The Kano State’s collaboration with Islamic Development Bank targets renovation of the Watari Dam, servicing the canals, and taking water to the farmlands. The Federal Government’s expansion targets increasing the irrigation sectors from six to eight: Sector One has 160 hectares, Sector Two has 168 hectares, Sector Three has 217 hectares, Sector Four has 72 hectares, Sector Five has 273 hectares, and Sector Eight has 73 hectares have all been completed.
It is Sector Six, which has 257 hectares, and Sector Seven, which has 343, whose work has sadly been suspended. These are scattered into meters owned by beleaguered subsistence farmers and small-scale producers. A group of people are so determined and hardworking that they get out of their skin to produce an incredible quantity of agricultural output.
Each hectare is estimated to produce 2.2 tons of maize or 3 tons of rice per farming season, and the irrigation system allows for four farming seasons annually. The monetary value of the agricultural output, assuming each hectare produces maize throughout the year, stands at ₦3.168 billion. And if all the hectares produce rice throughout the year, the estimate stands at ₦4.3 billion — which is a yield that’s far higher than what’s required to complete the project, all of which is being lost because the project hasn’t been completed, and worse yet, suspended.
When completed, the project’s multiplier effect will cut across revenue generation, job creation, stimulation of the rural economy, food production, poultry and cattle herding, stimulation of rural infrastructure, and discouraging the rampant rural-urban migration.
In the end, it certainly aligns with President Bola Ahmed Tinubu’s Renewed Hope agenda that is focused on diversification of the economy and revenue generation, among others, through domestic production and self-sufficiency in food production, to revise, revisit, and ensure spinal projects like the suspended Ɓagwai Irrigation Project are completed. Failure to do that will not only leave beleaguered farmers in a desperate state but also mean a project of national importance is left to rot away without remorse for the massive taxpayer resources invested in it already.
I’m very confident that such can never be the wish of the government under the watch of the president, Bola Ahmed Tinubu, the Governor of Kano State, Engr Abba Kabir Yusuf, the Minister of Agriculture and Rural Development, Hon. Abubakar Kyari, the Minister of Water Resources, Hon. Joseph Utsev, the Minister of Budget and Economic Planning, Hon. Atiku Bagudu, and the senator representing Kano North in the Red Chamber, who doubles as the Deputy Senate President, Hon. Barau I. Jibrin CFR, the member representing Ɓagwai and Shanono in the Green Chamber, Hon. Yusuf Badau, and the member representing Ɓagwai and Shanono in State House of Assembly, Hon. Halilu Ibrahim Kundila.
MA Iliasu is an economist writing from Kano. He can be reached via muhada102@gmail.com.